What’s the best way to start a new measurement with a specific trace?

There are many ways to start a new measurement. These methods will automatically select a trace for the new measurement: Double-click on a Trace in the Control Panel This is the most popular and most powerful way to start a measurement unless you’re using the Quantity Worksheet. If you display the Trace List or Trace […]

How do I create an eTakeoff project for a Sub-Hub project?

First you must view one of the plans for the project as described above. Then do the following: Select “File/Save” from the main menu (or press the “Save” button on the main toolbar). The “New Project Information” window will be displayed. show me Press the “Browse” button to create a new folder for the project. […]

How can I view different plans without going back to the Sub-Hub plan page?

When you view a plan from Sub-Hub, eTakeoff keeps a list of the other plans listed in the plan page. To view another plan, do the following: show me Note that the name of the current plan is displayed in the Project Toolbar. Press the down-arrow button to the right of the name to display […]

How do I view a Sub-Hub plan in eTakeoff?

First you must set your profile as described in the previous question. Then do the following: show me Navigate to the project in Sub-Hub. Select the plans you wish to view. Click on “eTakeoff Viewer”.

How do I configure Sub-Hub to interface with eTakeoff?

After you log in to Sub-Hub, do the following: show me Click on the “My Account” button at the top of the page. Select the “Maintenance” tab. Under the question “How would you like to view the high resolution files”, check the radio button next to “Take off Viewer”. Click on “Apply” (to the right) […]

I’m currently using CINView. How do I migrate to eTakeoff?

CINView is a special version of eTakeoff that was integrated with the CIN planroom. It is no longer supported and is not integrated with iSqFt. You need to install eTakeoff to have integration with iSqFt. If you’re using CINView, we recommend you install eTakeoff and begin using it for new projects. You can have both […]

How do I create an eTakeoff project for an iSqFt project?

First you must view one of the plans for the project as described above. Then do the following: Select “File/Save” from the main menu (or press the “Save” button on the main toolbar). The “New Project Information” window will be displayed. show me Press the “Browse” button to create a new folder for the project. […]

How can I view different plans without going back to the iSqFt plan page?

When you view a plan from iSqFt, eTakeoff keeps a list of the other plans listed in the Plan page. To view another plan, do the following: show me Note that the name of the current plan is displayed in the Project Toolbar. Press the down-arrow button to the right of the name to display […]

How do I view an iSqFt plan in eTakeoff?

First you must set your profile as described in the previous question. Then do the following: show me When you log in, be sure to select the “Keep me signed in” option. Search for and open any project in iSqFt. Click on the “Plans” tab. Simply click on the plan you wish to view. eTakeoff […]

How do I configure iSqFt to interface with eTakeoff?

After you log in to iSqFt, do the following: show me Click on “My Profile” in the “Administration” section of the left-hand column. Scroll down to the section on “Account Preferences”. Under “Plan Viewer”, check the radio button next to “eTakeoff”. Click on “Update Profile” to save the new setting. For iSqFt 10, it’s slightly […]